VOLTAGE INVERTER INSTALLATION

PROCEDURE


  1. INSTALL VOLTAGE INVERTER ASSEMBLY


    1. B0059OYN02

      Install the voltage inverter assembly with the 2 bolts as indicated by the arrows in the order shown in the illustration.

      Torque:
      6.8 N*m  { 69 kgf*cm, 60 in.*lbf }
    2. Attach the clamp and connect the connector.

  2. INSTALL NO. 1 TOOL BOX SUB-ASSEMBLY (w/ Spare Tire)

    Click here

  3. INSTALL NO. 1 TOOL BOX SUB-ASSEMBLY (w/o Spare Tire)

    Click here

  4. INSTALL NO. 2 TOOL BOX SUB-ASSEMBLY (w/ Spare Tire)

    Click here

  5. INSTALL NO. 2 TOOL BOX SUB-ASSEMBLY (w/o Spare Tire)

    Click here

  6. CONNECT REAR SEAT BACK BOARD CARPET ASSEMBLY RH


    1. Attach the 3 clips to connect the rear seat back board carpet assembly RH.

    2. Return the rear seatback assembly RH to the upright position.

  7. CONNECT REAR SEAT BACK BOARD CARPET ASSEMBLY LH


    1. Attach the 4 clips to connect the rear seat back board carpet assembly LH.

    2. Return the rear seatback assembly LH to the upright position.

  8. INSTALL DECK FLOOR BOX LH (w/ Spare Tire)

    Click here

  9. INSTALL DECK FLOOR BOX LH (w/o Spare Tire)

    Click here

  10. INSTALL DECK FLOOR BOX RH (w/ Spare Tire)

    Click here

  11. INSTALL DECK FLOOR BOX RH (w/o Spare Tire)

    Click here

  12. INSTALL SPARE TIRE (w/ Spare Tire)

    Click here

  13. INSTALL REAR DECK FLOOR BOX (w/ Spare Tire)

    Click here

  14. INSTALL NO. 3 DECK BOARD SUB-ASSEMBLY

    Click here

  15. INSTALL NO. 2 DECK BOARD SUB-ASSEMBLY

    Click here

  16. INSTALL DECK BOARD ASSEMBLY

    Click here