ГЕНЕРАТОР УСТАНОВКА

PROCEDURE


  1. INSTALL GENERATOR ASSEMBLY


    1. Install the generator assembly with the 3 bolts.

      Torque:
      25 N*m  { 255 kgf*cm, 18 ft.*lbf }

      Note

      Be careful that the wire harness of the crankshaft position sensor does not get caught between the cylinder block and generator when installing the generator.

    2. Connect the connector to the generator assembly.

    3. Connect the wire harness to terminal B with the nut.

      Torque:
      9.8 N*m  { 100 kgf*cm, 87 in.*lbf }
    4. Install the terminal cap.

    5. Connect the wire harness to the generator assembly with the bolt.

      Torque:
      7.7 N*m  { 79 kgf*cm, 68 in.*lbf }
  2. INSTALL WIRE HARNESS CLAMP BRACKET


    1. Install the wire harness clamp bracket with the bolt.

      Torque:
      13 N*m  { 133 kgf*cm, 10 ft.*lbf }
    2. Attach the wire harness clamp and connect the sensor connector.

  3. INSTALL FRONT DRIVE SHAFT ASSEMBLY RH

    Click here

  4. INSTALL FAN AND GENERATOR V BELT

    Click here

  5. INSTALL NO. 1 ENGINE COVER

    Click here

  6. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected.

    Click here