DC / DC CONVERTER INSTALLATION

PROCEDURE


  1. INSTALL POWER STEERING CONVERTER ASSEMBLY


    1. A0019YZ

      Install the converter with the 3 bolts.

      Torque:
      8.5 N*m  { 87 kgf*cm, 75 in.*lbf }
    2. A001DCOE02

      Connect the 2 converter connectors A and B, and securely lock the connectors.

  2. INSTALL BATTERY TRAY


    1. Install the battery tray with the 3 bolts.

      Torque:
      5.4 N*m  { 55 kgf*cm, 47 in.*lbf }
  3. INSTALL BATTERY


    1. Install the battery.

    2. Install the battery insulator.

    3. Install the battery clamp with the 2 nuts.

      Torque:
      5.4 N*m  { 55 kgf*cm, 47 in.*lbf }
    4. Connect the positive (+) battery cable to the battery terminal.

      Torque:
      5.6 N*m  { 57 kgf*cm, 50 in.*lbf }
    5. Connect the negative (-) battery cable to the battery terminal.

      Torque:
      5.6 N*m  { 57 kgf*cm, 50 in.*lbf }
  4. INSTALL COWL TOP VENTILATOR LOUVER

    Click here

  5. CHECK SRS WARNING LIGHT

    Click here

  6. PERFORM INITIALIZATION

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected Click here.