GENERATOR INSTALLATION

PROCEDURE


  1. INSTALL GENERATOR ASSEMBLY

    A001BLM

    1. Using an E8 "TORX" socket wrench, set the generator with the 2 stud bolts.

      Torque:
      10 N*m  { 102 kgf*cm, 7 ft.*lbf }
    2. A001F4R

      Install the generator with the 2 bolts and 2 nuts.

      Torque:
      43 N*m  { 438 kgf*cm, 32 ft.*lbf }
    3. A001A49

      Connect the generator connector.

    4. Connect the harness to the +B terminal with the nut.

      Torque:
      12 N*m  { 122 kgf*cm, 9 ft.*lbf }
  2. INSTALL V-RIBBED BELT

    Click here

  3. INSTALL INTAKE AIR CONNECTOR PIPE

    Click here

  4. INSTALL NO. 2 ENGINE UNDER COVER

    Click here

  5. INSTALL FRONT SUSPENSION MEMBER PROTECTOR LOWER

    Click here

  6. INSTALL NO. 1 ENGINE UNDER COVER

    Click here

  7. INSTALL NO. 1 AIR CLEANER INLET

    Click here

  8. INSTALL AIR CLEANER INLET COVER SUB-ASSEMBLY

    Click here

  9. INSTALL V-BANK COVER SUB-ASSEMBLY

    Click here

  10. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected Click here.

  11. INSTALL COWL TOP VENTILATOR LOUVER RH


    1. A0019TF

      Install the 6 clips and cowl top ventilator louver RH.

      Note

      If the cowl top ventilator louver RH is not properly installed, water may leak into the engine room and cause malfunctions. Therefore, make sure the cowl top ventilator louver RH is installed properly.