DESCRIPTION
The PTC heater is installed in the radiator in the heater unit and operates when cooling water temperature is low and normal heater effectiveness is insufficient.
The air conditioning amplifier switches the circuit in the PTC relay and operates the PTC heater when the operating conditions (cooling water temperature is below 55°C (131°F), setting temperature is MAX. HOT, air outlet damper position is FOOT or FOOT/DEF, and blower switch is not OFF) are met.
WIRING DIAGRAM
INSPECTION PROCEDURE
PROCEDURE
INSPECT FUSE (PTC HTR1, PTC HTR3, PTC HTR)
Remove the PTC HTR1 and PTC HTR3 fuses from the engine room No. 4 relay block, and PTC HTR H-fuse from the engine room No. 1 junction block.
Measure the resistance according to the value(s) in the table below.
| Standard resistance | ||||||||
|---|---|---|---|---|---|---|---|---|
|
| NG |
|
REPLACE FUSE |
| OK |
|
CHECK AIR CONDITIONING AMPLIFIER
Remove the air conditioning amplifier with its connectors still connected Click here.
Measure the voltage according to the value(s) in the table below.
| Standard voltage | |||||||
|---|---|---|---|---|---|---|---|
|
| NG |
|
REPLACE AIR CONDITIONING AMPLIFIER Click here |
| OK |
|
INSPECT PTC HEATER RELAY (PTC HTR1, PTC HTR3)
Remove the PTC heater relays from the No. 4 relay block.
Measure the resistance according to the value(s) in the table below.
| Standard resistance | ||||||||
|---|---|---|---|---|---|---|---|---|
|
| NG |
|
REPLACE PTC HEATER RELAY |
| OK |
|
CHECK HARNESS AND CONNECTOR (PTC HEATER RELAY - PTC HEATER)
Remove the PTC heater relays from the No. 4 relay block.
Disconnect the L40 PTC heater connector.
Measure the resistance according to the value(s) in the table below.
| Standard resistance | |||||||
|---|---|---|---|---|---|---|---|
|
| NG |
|
REPAIR OR REPLACE HARNESS OR CONNECTOR |
| OK |
|
CHECK PTC HEATER
Disconnect the L40 and L41 PTC heater connectors.
Measure the resistance according to the value(s) in the table below.
| Standard resistance | |||||||
|---|---|---|---|---|---|---|---|
|
| NG |
|
REPLACE PTC HEATER Click here |
| OK |
|
CHECK HARNESS AND CONNECTOR (AIR CONDITIONING AMPLIFIER - BODY GROUND)
Disconnect the L76 air conditioning amplifier connector.
Measure the resistance according to the value(s) in the table below.
| Standard resistance | |||||||
|---|---|---|---|---|---|---|---|
|
| NG |
|
REPAIR OR REPLACE HARNESS OR CONNECTOR |
| OK |
|
REPLACE AIR CONDITIONING AMPLIFIER Click here