GENERATOR(for 130 A Type) INSTALLATION

PROCEDURE


  1. INSTALL GENERATOR ASSEMBLY


    1. Install the generator assembly with the 2 bolts.

      Torque:
      52 N*m  { 530 kgf*cm, 38 ft.*lbf }
    2. Install the wire harness clamp bracket to the generator assembly with the bolt.

      Torque:
      8.0 N*m  { 82 kgf*cm, 71 in.*lbf }
    3. Connect the wire harness to terminal B with the nut.

      Torque:
      9.8 N*m  { 100 kgf*cm, 87 in.*lbf }
    4. Close the terminal cap.

    5. Connect the generator assembly connector.

  2. INSTALL V-RIBBED BELT

    Click here

  3. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected Click here.