ENGINE SWITCH INSTALLATION

PROCEDURE

  1. INSTALL ENGINE SWITCH (for LHD)

    1. Engage the 2 claws to install the engine switch.

  2. INSTALL NO. 1 SWITCH HOLE BASE (for LHD)

  3. INSTALL INSTRUMENT CLUSTER FINISH PANEL ASSEMBLY (for LHD)

  4. INSTALL CENTER INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY (for LHD)

  5. INSTALL LOWER NO. 2 INSTRUMENT PANEL FINISH PANEL (for LHD)

  6. INSTALL NO. 1 METER HOOD CLUSTER (for LHD)

  7. INSTALL ENGINE SWITCH (for RHD)

    1. Engage the 2 claws to install the engine switch.

  8. INSTALL NO. 2 SWITCH HOLE BASE (for RHD)

  9. INSTALL LOWER INSTRUMENT CLUSTER FINISH PANEL ASSEMBLY (for RHD)

  10. INSTALL UPPER INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY (for RHD)

  11. INSTALL INSTRUMENT SIDE PANEL RH (for RHD)

  12. INSTALL INSTRUMENT CLUSTER FINISH PANEL ASSEMBLY (for RHD)

  13. INSTALL NO. 1 METER HOOD CLUSTER (for RHD)

  14. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

    Note:

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected.

    Click hereClick hereClick here