CAUTION / NOTICE / HINT
Tech Tips
Use the same procedure for both the RH and LH sides.
The following procedure is for the LH side.
PROCEDURE
INSTALL NO. 1 ROOF DRIP SIDE FINISH MOULDING CLIP
Note
If reusing the clips, do not remove the double-sided tape remaining on the clips and where the clips will be installed on the body.
If installing new clips, remove the double-sided tape remaining where the clips will be installed on the body and clean the body with a non-residue solvent.
| *1 | Adhesive |
| *a | 2 to 3 mm (0.0787 to 0.118 in.) Bead of Adhesive |
Apply a 2 to 3 mm (0.0787 to 0.118 in.) bead of adhesive (3M DP-105 or equivalent) to new No. 1 roof drip side finish moulding clip.
Tech Tips
Adhesive strength (tensile strength): 13.7 MPa (140 kgf/cm2, 1987 psi) or more (when the temperature is 23°C (73°F)).
Press and install the No. 1 roof drip side finish moulding clip.
Install the clips to the positions on the roof panel shown in the illustration. Determine the locations and firmly press and install the No. 1 roof drip side finish moulding clip after lightly applying adhesive (3M DP-105 or equivalent).
| Standard Dimension | ||||||||
|---|---|---|---|---|---|---|---|---|
|
| *1 | Out Side Panel | *2 | Roof Panel |
Install the roof drip center side finish moulding when 40 minutes or more have elapsed after pressing and installing the No. 1 roof drip side finish moulding clips.
Tech Tips
Initial hardening time: 40 minutes
Complete hardening time: 24 hours
INSTALL CENTER ROOF DRIP SIDE FINISH MOULDING
Engage the 2 clips and install the center roof drip side finish moulding, as shown in the illustration.