AIR SWITCHING VALVE INSTALLATION


  1. INSTALL AIR SWITCHING VALVE ASSEMBLY


    1. Install the air switching valve assembly with 2 new nuts.

      Torque:
      26 N*m  { 265 kgf*cm, 19 ft.*lbf }
    2. Connect the air switching valve connector.

  2. INSTALL NO. 4 INTAKE PIPE


    1. B007Q0XE04

      Install 2 new gaskets and the No. 4 intake pipe with 4 new nuts in the order shown in the illustration. Tighten the nuts labeled 1 and 3 to the torque specification again.

      Torque:
      26 N*m  { 265 kgf*cm, 19 ft.*lbf }
    2. Check that the nuts are tightened to the torque specification.

      Note

      Tightening the nuts only once is not enough to tighten them to the torque specification.

  3. INSTALL NO. 1 EXHAUST MANIFOLD HEAT INSULATOR


    1. Install the No. 1 exhaust manifold heat insulator with the 4 bolts.

      Torque:
      12 N*m  { 122 kgf*cm, 9 ft.*lbf }
  4. INSTALL AIR PUMP INLET PIPE


    1. Install the air pump inlet pipe with the 2 bolts.

      Torque:
      18 N*m  { 184 kgf*cm, 13 ft.*lbf }
    2. Connect the No. 5 air hose, and slide the clamp to secure the hose.

    3. Connect the No. 6 air hose, and slide the clamp to secure the hose.

  5. INSTALL BATTERY SERVICE HOLE COVER

  6. INSTALL ENGINE SERVICE HOLE SUB COVER SUB-ASSEMBLY


    1. Install the engine service hole cover sub-assembly with the 5 bolts.

      Torque:
      13 N*m  { 133 kgf*cm, 10 ft.*lbf }
  7. INSTALL FRONT DOOR SCUFF PLATE RH

  8. INSTALL FRONT SEAT ASSEMBLY RH

    Click here

  9. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected Click here.

  10. PERFORM INITIALIZATION

    Click here