OIL PUMP (w/o EGR Cooler) INSTALLATION

Note


  • When replacing the injectors (including shuffling the injectors between the cylinders), common rail or cylinder head, it is necessary to replace the injection pipes with new ones.

  • When replacing the fuel supply pump, common rail, cylinder block, cylinder head, cylinder head gasket or timing gear case, it is necessary to replace the fuel inlet pipe with a new one.


  1. INSTALL TIMING GEAR CASE ASSEMBLY


    1. A01DWKHE01

      Install 2 new O-rings to the cylinder block.

    2. Remove any old seal packing (FIPG material) from the timing gear case and cylinder block.

    3. Set a new gasket to the timing gear case.

    4. A01DW8HE11

      Apply seal packing to the areas shown in the illustration.

      Seal packing
      Toyota Genuine Seal Packing Black, Three Bond 1207B or equivalent
      Seal diameter
      4 mm (0.15 in.)

      Note


      • After applying seal packing, install the timing gear case within 3 minutes and tighten the bolts within 15 minutes.

      • Do not start the engine for at least 2 hours after the installation.

    5. A01E21QE01

      Align the "2" timing marks of the No. 1 balance shaft driven gear and oil pump drive gear, and install the timing gear case to the cylinder block.

    6. Install the timing gear case with the 8 bolts and union bolt.

      Torque:
      13 N*m  { 133 kgf*cm, 10 ft.*lbf, for bolt }
      16 N*m  { 163 kgf*cm, 12 ft.*lbf, for union bolt }
    7. Make sure that the oil pump drive gear rotates smoothly.

      Note

      If the gear does not rotate smoothly, remove the 8 bolts and union bolt to release the gear. Then install the bolts and gear again.

  2. INSTALL OIL STRAINER SUB-ASSEMBLY


    1. Install a new gasket and the oil strainer with the 2 bolts and nut.

      Torque:
      8.0 N*m  { 82 kgf*cm, 71 in.*lbf }
  3. INSTALL OIL PAN SUB-ASSEMBLY


    1. Remove any old seal packing (FIPG) from the oil pan and cylinder block.

    2. A01DX2KE08

      Apply seal packing to the areas shown in the illustration.

      Seal packing
      Toyota Genuine Seal Packing Black, Three Bond 1207B or equivalent
      Seal diameter
      4 mm (0.15 in.)

      Note


      • After applying seal packing, install the oil pan within 3 minutes and tighten the bolts within 15 minutes.

      • Do not start the engine for at least 2 hours after the installation.

    3. Install the oil pan with the 22 bolts and 2 nuts.

      Torque:
      12 N*m  { 122 kgf*cm, 9 ft.*lbf }
  4. INSTALL FUEL SUPPLY PUMP ASSEMBLY

    A01E0JEE01

    1. Check that the injection gear in the timing gear case moves back and forth smoothly.

    2. Install a new O-ring to the pump.

    3. Apply a light coat of engine oil to the O-ring.

    4. A01E2NBE01

      Align the set key on the drive shaft with the groove of the injection gear.

    5. A01E141E01

      Install the pump with the 2 nuts.

      Torque:
      21 N*m  { 214 kgf*cm, 15 ft.*lbf }
    6. Set a new O-ring before tightening the set nut.

    7. A01E0MBE01

      Using SST, hold the crankshaft pulley and install the set nut.

      SST
      09213-58013
      09330-00021
      Torque:
      64 N*m  { 653 kgf*cm, 47 ft.*lbf }
    8. A01DZC9E01

      Move the pump drive shaft pulley back and forth to check the thrust clearance of the injection pump drive shaft.

      Thrust clearance
      0.15 to 0.55 mm (0.0059 to 0.0217 in.)

      If the clearance is not within the specified range, disassemble and reassemble the supply pump and pump drive shaft pulley. Then repeat the step above.

    9. A01DXJEE01

      Connect the 2 connectors.

    10. A01DYSWE01

      Connect the 2 fuel hoses.

    11. A01E008E06

      Temporarily install the fuel inlet pipe with the union nuts.

      Note


      • If the supply pump is replaced, the fuel inlet pipe must be replaced.

      • Keep the fuel inlet pipe free of foreign matter.

    12. Using a 17 mm union nut wrench, tighten the injection pipe union nut on the common rail side.

      Torque:
      32 N*m  { 326 kgf*cm, 24 ft.*lbf, for use with union nut wrench }
      35 N*m  { 357 kgf*cm, 26 ft.*lbf, for use without union nut wrench }

      Tech Tips

      Use a torque wrench with a fulcrum length of 30 cm (11.81 in.).

    13. Using a 17 mm union nut wrench, tighten the injection pipe union nut on the supply pump side.

      Torque:
      32 N*m  { 326 kgf*cm, 24 in.*lbf, for use with union nut wrench }
      35 N*m  { 357 kgf*cm, 26 ft.*lbf, for use without union nut wrench }

      Use a torque wrench with a fulcrum length of 30 cm (11.81 in.).

    14. Install the oil level gauge guide with the 2 bolts.

      Torque:
      8.0 N*m  { 82 kgf*cm, 71 in.*lbf }
    15. A01DW6AE01

      Install the clamp with the bolt.

      Torque:
      5.0 N*m  { 51 kgf*cm, 44 in.*lbf }
  5. INSTALL INJECTION GEAR


    1. A01E0IQE01

      Align the "3" timing marks of the injection gear and balance No. 2 shaft driven gear, and install the injection gear.

      Note

      Fit the key (protrusion) of the supply pump to the key slot of the injection gear.

    2. Set a new O-ring and then temporarily install the nut. Using your hand, check the thrust clearance of the supply pump drive shaft by driving the injection gear.

      Thrust clearance
      0.15 to 0.55 mm (0.0059 to 0.0217 in.)

      Tech Tips

      If the clearance is not within the specified range, remove the injection gear again and reinstall it.

  6. INSTALL CRANKSHAFT TIMING GEAR

    A01E1QCE01

    1. Align the "1" timing marks of the oil pump drive gear and crankshaft timing gear as shown in the illustration.

    2. Using SST, install the crankshaft timing gear.

      SST
      09223-00010
  7. INSTALL NO. 1 IDLE GEAR


    1. A01DVPDE02

      Install the No. 1 idle gear shaft to the cylinder block.

    2. A01DY8JE01

      Align the "4" timing marks of the No. 1 idle gear and injection gear, as shown in the illustration.

    3. Align the "5" timing marks of the No. 1 idle gear and crankshaft timing gear, and install the No. 1 idle gear, as shown in the illustration.

    4. Install the idle gear thrust plate with the 2 bolts.

      Torque:
      50 N*m  { 510 kgf*cm, 37 ft.*lbf }
    5. Remove the service bolt.

    6. Install the No. 1 crankshaft sensor plate.

  8. INSTALL TIMING GEAR COVER


    1. A01DVAGE01

      Install a new O-ring to the timing gear case.

    2. Remove any old seal packing (FIPG material) from the timing gear cover.

    3. A01DYL9E04

      Apply seal packing to the areas shown in the illustration.

      Seal packing
      Toyota Genuine Seal Packing Black, Three Bond 1207B or equivalent
      Seal diameter
      4 mm (0.15 in.)

      Note


      • After applying seal packing, install the gear cover within 3 minutes and tighten the bolts and nuts within 15 minutes.

      • Do not start the engine for at least 2 hours after the installation.

    4. Install the cover with the 14 bolts and 2 nuts.

      Torque:
      13 N*m  { 133 kgf*cm, 10 ft.*lbf }
    5. Install the No. 1 vacuum transmitting pipe with the bolt.

      Torque:
      8.0 N*m  { 82 kgf*cm, 71 in.*lbf }
  9. INSTALL CRANKSHAFT POSITION SENSOR


    1. Install the crankshaft position sensor with the bolt.

      Torque:
      8.5 N*m  { 87 kgf*cm, 75 in.*lbf }
  10. INSTALL CAMSHAFT POSITION SENSOR


    1. Install the camshaft position sensor with the bolt.

      Torque:
      8.5 N*m  { 87 kgf*cm, 75 in.*lbf }
  11. INSTALL CRANKSHAFT PULLEY


    1. A01DZE1E02

      Align the pulley set key with the key groove of the pulley.

    2. Using SST, install the pulley bolt.

      SST
      09213-58014
      09330-00021
      Torque:
      365 N*m  { 3722 kgf*cm, 269 ft.*lbf }
  12. INSTALL PUMP DRIVE SHAFT PULLEY


    1. Install a new O-ring to the supply pump.

    2. Temporarily install the supply pump with the nut.

    3. A01E0MBE01

      Using SST, hold the crankshaft pulley and tighten the nut.

      SST
      09213-58014
      09330-00021
      Torque:
      64 N*m  { 653 kgf*cm, 47 ft.*lbf }
    4. A01DVN8E01

      Install the No. 2 camshaft timing pulley flange and pump drive shaft pulley with the 4 bolts.

      Torque:
      31 N*m  { 316 kgf*cm, 23 ft.*lbf }
    5. A01E0PAE01

      Using a dial indicator, check the thrust clearance of the pump drive shaft while moving the pump drive shaft pulley back and forth.

      Thrust clearance
      0.15 to 0.55 mm (0.0059 to 0.0217 in.)

      Tech Tips

      If the clearance is not within the specified range, remove and reinstall the supply pump and pump drive shaft pulley. Then repeat the step above.

  13. INSTALL VANE PUMP ASSEMBLY


    1. Install a new O-ring to the vane pump.

    2. Install the vane pump with the 2 nuts.

      Torque:
      41 N*m  { 418 kgf*cm, 30 ft.*lbf }
  14. INSTALL VACUUM PUMP ASSEMBLY


    1. Install 2 new O-rings to the vacuum pump.

    2. Install the vacuum pump with the 2 nuts.

      Torque:
      21 N*m  { 210 kgf*cm, 15 ft.*lbf }
  15. INSTALL WATER PUMP ASSEMBLY

    A01DWA8

    1. Install a new gasket and the water pump with the 5 bolts and 2 nuts.

      Torque:
      13 N*m  { 133 kgf*cm, 10 ft.*lbf }
  16. INSTALL NO. 2 TIMING BELT COVER


    1. A01E1J8E01

      Apply seal packing (FIPG) to the specified areas shown in the illustration.

      Seal packing
      Toyota Genuine Seal Packing Black, Three Bond 1207B or equivalent

      Note

      After applying FIPG, install the No. 2 timing belt cover within 3 minutes and tighten its bolts and nut within 15 minutes.

    2. Install the No. 2 timing belt cover with the 4 bolts and nut.

      Torque:
      10 N*m  { 102 kgf*cm, 7 ft.*lbf }
  17. INSTALL NO. 1 TIMING BELT IDLER SUB-ASSEMBLY


    1. Install the timing belt idler and a new spacer with the bolt.

      Torque:
      35 N*m  { 357 kgf*cm, 26 ft.*lbf }
  18. INSTALL CAMSHAFT TIMING PULLEY


    1. A01DV9RE01

      Install the camshaft timing pulley.

    2. Fasten the bolt of the camshaft timing pulley by holding the camshaft with a wrench.

      Torque:
      98 N*m  { 1000 kgf*cm, 72 ft.*lbf }
  19. INSTALL CYLINDER HEAD COVER SUB-ASSEMBLY


    1. A01DZAXE01

      Install 4 new No. 3 cylinder head cover gaskets to the cylinder head cover in the directions shown in the illustration.

      Note


      • Do not install the No. 3 cylinder head cover gaskets at an angle.

      • Check that there is no foreign matter at the installation location of the No. 3 cylinder head cover gaskets.

    2. Remove any old seal packing (FIPG) material from the cylinder head.

    3. A01E1YSE03

      Apply seal packing to the specific areas shown in the illustration.

      Seal packing
      Toyota Genuine Seal Packing Black, Three Bond 1207B or equivalent

      Note


      • Remove any oil from the contact surface.

      • Install the head cover within 3 minutes after applying seal packing.

      • Do not start the engine for at least 2 hours after installing the seal packing.

    4. Install a new cylinder head cover gasket and the cylinder head cover with the 10 bolts and 2 nuts.

      Torque:
      9.0 N*m  { 92 kgf*cm, 80 in.*lbf }
    5. Install 4 new nozzle holder seals.

    6. Connect the ventilation hose.

    7. Connect the 4 connectors and install the 3 bolts.

      Torque:
      13 N*m  { 127 kgf*cm, 9 ft.*lbf }
  20. INSTALL NO. 4 INJECTION PIPE SUB-ASSEMBLY

    Note


    • When replacing an injector, it is necessary to replace the 4 injection pipes with new ones.

    • Keep the joints of the injection pipe clean.


    1. Temporarily install the No. 4 injection pipe with the union nuts.

    2. Install the 2 bolts.

      Torque:
      13 N*m  { 130 kgf*cm, 9 ft.*lbf }

      Note


      • If an injection pipe clamp is removed from the No. 4 injection pipe, replace the injection clamp with a new one.

      • Make sure that the inner-rubbers of the injection pipe fit inside the clamps.

      • When installing the pipe, check that the inner-rubbers and the clamps are in their proper positions.

    3. A01E0ONE01

      Using a 17 mm union nut wrench, tighten the injection pipe union nut on the common rail side.

      Torque:
      35 N*m  { 357 kgf*cm, 26 ft.*lbf }

      Note

      Use the formula to calculate special torque values for situations where a union nut wrench is combined with a torque wrench Click here.

    4. Using a 17 mm union nut wrench, tighten the injection pipe union nuts on the injector side.

      Torque:
      35 N*m  { 357 kgf*cm, 26 ft.*lbf }

      Note

      Use the formula to calculate special torque values for situations where a union nut wrench is combined with a torque wrench Click here.

  21. INSTALL NO. 1, NO. 2 AND NO. 3 INJECTION PIPE SUB-ASSEMBLY

    Note


    • When replacing an injector, it is necessary to replace the 4 injection pipes with new ones.

    • Keep the joints of the injection pipe clean.


    1. Temporarily install the No. 1, No. 2 and No. 3 injection pipes with the union nuts.

    2. A01E2KZE01

      Install the No. 2 and No. 3 injection pipe clamps with the bolt and 2 nuts, as shown in the illustration.

      Torque:
      5.0 N*m  { 51 kgf*cm, 44 in.*lbf }

      Tech Tips

      If the painted mark on the No. 1 injection pipe has disappeared, use the illustration as a reference to install the clamps.

    3. A01DZLXE01

      Using a 17 mm union nut wrench, tighten the injection pipe union nuts on the common rail side.

      Torque:
      35 N*m  { 357 kgf*cm, 26 ft.*lbf }

      Note

      Use the formula to calculate special torque values for situations where a union nut wrench is combined with a torque wrench Click here.

    4. Using a 17 mm union nut wrench, tighten the injection pipe union nuts on the injector side.

      Torque:
      35 N*m  { 357 kgf*cm, 26 ft.*lbf }

      Note

      Use the formula to calculate special torque values for situations where a union nut wrench is combined with a torque wrench Click here.

  22. INSTALL FUEL INLET PIPE SUB-ASSEMBLY


    1. A01E008E05

      Temporarily install the fuel inlet pipe with the union nuts.

      Note


      • When replacing the common rail, it is necessary to replace the 4 injection pipes and fuel inlet pipe with new ones.

      • Be careful that dust, dirt or any other foreign matter does not contact the joint area of the fuel inlet pipe.

    2. Using a 17 mm union nut wrench, tighten the fuel inlet pipe union nut on the common rail side.

      Torque:
      35 N*m  { 357 kgf*cm, 26 ft.*lbf }

      Note

      Use the formula to calculate special torque values for situations where a union nut wrench is combined with a torque wrench Click here.

    3. Using a 17 mm union nut wrench, tighten the fuel inlet pipe union nut on the supply pump side.

      Torque:
      35 N*m  { 357 kgf*cm, 26 ft.*lbf }

      Note

      Use the formula to calculate special torque values for situations where a union nut wrench is combined with a torque wrench Click here.

    4. Install a new O-ring to the engine oil level dipstick guide.

    5. Install the engine oil level dipstick guide with the bolt.

      Torque:
      8.0 N*m  { 82 kgf*cm, 71 in.*lbf }
    6. Install the clamp with the bolt.

      Torque:
      5.0 N*m  { 51 kgf*cm, 44 in.*lbf }
    7. Install the engine oil level dipstick.

  23. INSTALL MANIFOLD STAY

    A01DWQ8E01

    1. Install the stay with the 2 bolts.

      Torque:
      19 N*m  { 194 kgf*cm, 14 ft.*lbf }

      Tech Tips

      The stay's indented area (labeled A) must face the manifold.

  24. INSTALL NO. 1 COMPRESSOR MOUNTING BRACKET


    1. Install the No. 1 compressor mounting bracket with the 4 bolts.

      Torque:
      45 N*m  { 459 kgf*cm, 33 ft.*lbf }
  25. INSTALL V-RIBBED BELT TENSIONER ASSEMBLY


    1. A01DYTCE04
      Text in Illustration
      *1 V-ribbed Belt Tensioner
      *2 Cylinder Block

      Install the tensioner with the 4 bolts.

      Torque:
      21 N*m  { 214 kgf*cm, 15 ft.*lbf }

      Tech Tips

      Firmly press and hold the tensioner against the cylinder block to eliminate any gaps in the areas labeled A in the illustration. Then uniformly tighten the 4 bolts.

  26. INSTALL GENERATOR BRACKET


    1. Install the generator bracket with the bolt.

      Torque:
      25 N*m  { 255 kgf*cm, 18 ft.*lbf }
  27. INSTALL GENERATOR ASSEMBLY

    A01DXLFE01

    1. Install the generator with the 2 bolts.

      Torque:
      62 N*m  { 632 kgf*cm, 46 ft.*lbf, for bolt A }
      25 N*m  { 255 kgf*cm, 18 ft.*lbf, for bolt B }
    2. Install the generator wire with the nut.

      Torque:
      9.8 N*m  { 100 kgf*cm, 87 in.*lbf }
    3. Connect the generator connector.

  28. INSTALL NO. 2 IDLE PULLEY ASSEMBLY

  29. INSTALL NO. 1 TIMING BELT TENSIONER ASSEMBLY

  30. INSTALL TIMING BELT

    A01E2G9E02

    1. Check that the timing marks are aligned as shown in the illustration.

      Tech Tips

      If reusing the timing belt, align the points marked during removal, and install the belt with the arrow pointing in the direction of engine revolution.

      Note


      • The engine should be cold.

      • When turning the crankshaft, the valve heads will hit against the piston's top position. Do not turn it more than necessary.

    2. Using a 10 mm hexagon wrench, install the and timing belt idler pulley and new washer with the bolt.

      Torque:
      35 N*m  { 357 kgf*cm, 26 ft.*lbf }
    3. Check that the idler pulley moves smoothly.

      If it does not move smoothly, check the idler sub-assembly and washer.

    4. Install the timing belt to the pump drive shaft pulley, camshaft timing pulley and No. 1 timing belt idler in sequence.

    5. A01E2YJE01

      Place the tensioner upright. Then set the press to the top of the tensioner.

      Note


      • Do not scratch or deform the rod end.

      • Press in the tensioner rod upward.

      • Protect the tip of the push rod with a cloth in order to prevent damage.

    6. Using a press, slowly push in the push rod using 981 to 9800 N (100 to 999 kgf, 220 to 2203 lbf) of force.

      Note

      Do not impose a load of over 9800 N (999 kgf, 2203 lbf) to the push rod.

    7. Align the holes of the push rod and housing. Then pass a 1.27 mm hexagon wrench through the holes to keep the setting position of the push rod.

    8. Install the timing belt tensioner with the 2 bolts while pushing the idler pulley toward the timing belt.

    9. Tighten the 2 bolts.

      Torque:
      13 N*m  { 133 kgf*cm, 10 ft.*lbf }

      Note

      Uniformly tighten the 2 bolts and install the tensioner.

    10. A01DZUHE01

      Remove the 1.5 mm hexagon wrench from the tensioner.

    11. A01DWQTE02

      Turn the crankshaft clockwise 720° and check that the timing marks are aligned as shown in the illustration.

  31. INSTALL NO. 1 TIMING BELT COVER


    1. Install the timing belt cover with the 6 bolts.

      Torque:
      6.0 N*m  { 61 kgf*cm, 53 in.*lbf }
    2. Install the wire harness clamp.

    3. Install the water hose clamp with the bolt.

      Torque:
      18 N*m  { 184 kgf*cm, 13 ft.*lbf }
  32. INSTALL ENGINE ASSEMBLY

    Click here