FLOOR SHIFT ASSEMBLY INSTALLATION


  1. INSTALL FLOOR SHIFT ASSEMBLY

    A01E08LE01

    1. Install the floor shift with the 4 bolts.

      Torque:
      14 N*m  { 143 kgf*cm, 10 ft.*lbf }
    2. A01E2OPE01

      Connect the clamp and 2 connectors.

    3. Move the shift lever to L.

    4. Connect the transmission control cable.

  2. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

  3. PERFORM INITIALIZATION


    1. Perform initialization Click here.

      Note

      Certain systems need to be initialized after disconnecting and reconnecting the cable from the negative (-) battery terminal.

  4. ADJUST SHIFT LEVER POSITION


    1. Adjust the shift lever position Click here.

  5. INSPECT SHIFT LEVER POSITION


    1. Inspect the shift lever position Click here.

  6. INSTALL CONSOLE BOX ASSEMBLY


    1. Install the console box assembly Click here.