AIR SWITCHING VALVE(for Bank 2) INSTALLATION

PROCEDURE

  1. INSTALL AIR SWITCHING VALVE ASSEMBLY

    1. A231415C01

      *1

      No. 3 Air Tube

      *2

      Air Switching Valve

      *3

      Claw

      Install a new gasket and the air switching valve with the 3 bolts.

      24 N*m

      245 kgf*cm

      18 ft.*lbf

      Note:

      Make sure the claws of the gasket are not caught between the air switching valve and No. 3 air tube.

    2. Install the 2 bolts.

      10 N*m

      102 kgf*cm

      7 ft.*lbf

    3. Connect the wire harness clamp bracket with the bolt.

      8.0 N*m

      82 kgf*cm

      71 in.*lbf

    4. Attach the wire harness clamp and connect the air switching valve connector.

  2. CONNECT NO. 1 AIR INJECTION SYSTEM HOSE

    1. A231416C01

      *1

      Projection

      *2

      Paint Mark

      Align the paint mark with the projection and connect the No. 1 air injection system hose.

      Tip:

      Make sure the direction of the hose clamp is as shown in the illustration.

  3. CONNECT NO. 3 VENTILATION HOSE

    1. A231417C01

      *1

      Paint Mark

      *a

      Front

      Connect the No. 3 ventilation hose.

      Tip:

      The direction of the hose clamp is indicated in the illustration.

  4. INSTALL AIR CLEANER CAP AND HOSE

  5. INSTALL V-BANK COVER SUB-ASSEMBLY

  6. INSTALL ENGINE ROOM SIDE COVER