STARTER(for 1.0 kW Type) INSTALLATION
PROCEDURE
INSTALL FLYWHEEL HOUSING SIDE COVER
Install the flywheel housing side cover to the cylinder block.
INSTALL STARTER ASSEMBLY
Install the starter assembly with the 2 bolts.
37 N*m
377 kgf*cm
27 ft.*lbf
Connect the starter connector.
Connect the starter wire with the nut.
9.8 N*m
100 kgf*cm
87 in.*lbf
Connect the terminal cap.
INSTALL NO. 1 TRANSMISSION CONTROL CABLE BRACKET (for CVT)
CONNECT TRANSMISSION CONTROL CABLE ASSEMBLY (for CVT)
Connect the transmission control cable assembly to the No. 1 transmission control cable bracket with a new clip.
INSTALL BATTERY BRACKET REINFORCEMENT
Install the battery bracket reinforcement with the 2 bolts.
20 N*m
204 kgf*cm
15 ft.*lbf
INSTALL FRONT BATTERY BRACKET
Install the front battery bracket with the 4 bolts.
20 N*m
204 kgf*cm
15 ft.*lbf
Attach the 3 wire harness clamps.
CONNECT RADIATOR HOSE SUB-ASSEMBLY
Connect the radiator hose sub-assembly to the front battery bracket with the 2 bolts.
19 N*m
194 kgf*cm
14 ft.*lbf
INSTALL BATTERY TRAY
INSTALL BATTERY
INSTALL BATTERY CLAMP SUB-ASSEMBLY
Attach the hook of the battery clamp sub-assembly to the front battery bracket.
Partially tighten the nut and temporarily install the bolt.
Adjust the battery clamp sub-assembly position.
Tighten the nut and bolt.
for bolt
17 N*m
173 kgf*cm
13 ft.*lbf
for nut
4.9 N*m
50 kgf*cm
43 in.*lbf
INSTALL AIR CLEANER CAP SUB-ASSEMBLY
CONNECT CABLE TO POSITIVE BATTERY TERMINAL
CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
Note:When disconnecting the cable, some systems need to be initialized after the cable is reconnected.
Click hereClick hereClick hereClick hereClick hereClick here
INSTALL NO. 2 CYLINDER HEAD COVER
INSTALL NO. 1 ENGINE UNDER COVER