GENERATOR INSTALLATION

PROCEDURE

  1. INSTALL GENERATOR ASSEMBLY

    1. Install the wire harness clamp bracket to the generator assembly with the bolt.

      10 N*m

      102 kgf*cm

      7 ft.*lbf

    2. Using an E8 "TORX" socket wrench, temporarily install the generator assembly with the stud bolt.

      10 N*m

      102 kgf*cm

      7 ft.*lbf

    3. Install the generator assembly with the bolt and 2 nuts.

      25 N*m

      255 kgf*cm

      18 ft.*lbf

    4. Engage the wire harness clamp.

    5. Connect the generator assembly connector.

    6. Connect the wire harness to terminal B with the nut.

      9.8 N*m

      100 kgf*cm

      87 in.*lbf

    7. Install the terminal cap.

  2. INSTALL V-RIBBED BELT

  3. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

    Note:

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected.