FRAME SIDE RAIL FRONT ASSEMBLY REPLACEMENT

B002MM3

B002MKB

Tech Tips


  • Use the same procedure for the RH and LH.

  • The procedure listed below is for the RH.


  1. REMOVAL

    Symbol Meaning
    B002MHS Cut with Disc Sander etc.
    B002MR2C01
    *A FRONT *B UPPER
    *C LH - -
  2. INSTALLATION

    Symbol Meaning
    B002MP9 Fillet Weld

    1. Temporarily install the new parts and measure each part of the new parts in accordance with the body dimension diagram. (See the body dimensions)

    2. Make sure that proper welding can be performed by setting up the welding conditions as necessary before performing work.

    3. To prevent heat deformation, weld the right and left side of each part before continuing to the next part.

    4. Make sure that the welding bead at A is overlapped.

      B002MHCC01
      *A FRONT *B UPPER
      *C LH - -
      *1 SIDE RAIL EXTENSION ASSEMBLY - -
      *a 146 mm (5.75 in.) *b 172 mm (6.77 in.)
    5. After applying the top coat, apply anti-rust agent to the internal panel portion of the closed section structural weld points.