With the quarter panel assembly removed.
REMOVAL
| Symbol Meaning | |
|---|---|
|
Remove Weld Points |
|
Cut and Join Location |
| *a | 180 mm (7.09 in.) | - | - |
INSTALLATION
| Symbol Meaning | |
|---|---|
|
Plug Weld |
|
Cut and Join Location |
|
Butt Weld |
If the entire supply part is not needed, remove the part of the supply part that is needed.
| *1 | QUARTER LOCK PILLER REINFORCEMENT LOWER | - | - |
| *a | 120 mm (4.72 in.) | - | - |
Before temporarily installing the new parts, weld the quarter lock piller reinforcement lower, quarter lock pillar reinforcement sub-assembly and quarter inner ECU bracket No.2 or quarter inner ECU bracket No.1 with the standard number of welding points.
| *1 | QUARTER LOCK PILLER REINFORCEMENT LOWER | *2 | QUARTER LOCK PILLAR REINFORCEMENT SUB-ASSEMBLY |
| *3 | QUARTER INNER ECU BRACKET NO.2(LH) | *4 | QUARTER INNER ECU BRACKET NO.1(RH) |
After applying the top coat, apply anti-rust agent to the internal panel portion of the closed section structural weld points.