TRANSMISSION CONTROL CABLE INSTALLATION


  1. INSTALL TRANSMISSION CONTROL CABLE ASSEMBLY

    Note

    Before installing the transmission control cable assembly, check that the park/neutral position switch and shift lever are in neutral.


    1. A01ISKE

      Put the transmission control cable into the cabin and connect the transmission control cable with the 2 nuts.

      Torque:
      5.0 N*m  { 51 kgf*cm, 44 in.*lbf }
    2. A01ISE1

      Connect the transmission control cable support with the bolt.

      Torque:
      5.0 N*m  { 51 kgf*cm, 44 in.*lbf }
    3. A01IRDT

      Connect the transmission control cable to the bracket with a new clip.

    4. Connect the transmission control cable to the control shaft lever with the nut.

      Torque:
      12 N*m  { 122 kgf*cm, 9 ft.*lbf }
    5. Turn the nut of the transmission control cable 180° counterclockwise. While holding the nut in place, push in the stopper until the stopper clicks twice.

      A01ITS8E01
      Text in Illustration
      *1 Stopper *2 Nut
    6. Install the outer part of the transmission control cable to the shift lever retainer. Check that the spring is positioned at "A" and push in the stopper.

      A01IQUME01
      Text in Illustration
      *1 Stopper *2 Nut
      *3 Shift Lever Retainer *4 Spring

      Tech Tips

      If the stopper cannot be pushed in, slightly turn the nut clockwise and then push in the stopper again.

    7. A01IT4JE01

      Push the 2 claws together at the top of the transmission control cable lock piece. While holding the 2 claws together, push the 2 lugs on the bottom of the lock piece toward each other and upward to pull out the lock piece.

    8. A01IQD7E01
      Text in Illustration
      *1 Lock Piece

      Connect the end of the cable to the shift lever assembly.

      Note


      • Make sure that the lock piece is pulled up.

      • Push on the end of the cable all the way to the base of the pin.

    9. A01ISRAE01
      Text in Illustration
      *1 Lock Piece
      *2 Adjuster Case

      Push the lock piece into the adjuster case.

      Note

      Securely push in the lock piece until it locks.

  2. INSTALL LOWER NO. 1 INSTRUMENT PANEL FINISH PANEL


    1. Install the lower No. 1 instrument panel finish panel Click here.

  3. INSTALL FRONT FLOOR NO. 1 HEAT INSULATOR

    A01IUDN

    1. Install the heat insulator with the 3 nuts.

      Torque:
      5.5 N*m  { 56 kgf*cm, 49 in.*lbf }
  4. INSTALL FRONT FLOOR NO. 2 HEAT INSULATOR

    A01IRFR

    1. Install the heat insulator with the 3 nuts.

      Torque:
      5.5 N*m  { 56 kgf*cm, 49 in.*lbf }
  5. INSTALL FRONT EXHAUST PIPE ASSEMBLY


    1. Check the free length of the compression spring.


      1. A01IN16

        Using a vernier caliper, measure the free length of the compression spring.

        Minimum length
        41.5 mm (1.63 in.)

        If the free length is less than the minimum, replace the compression spring.

    2. Connect the front exhaust pipe to the 3 exhaust pipe supports.

    3. Install a new gasket to the front exhaust pipe.

    4. Install the front exhaust pipe with the 2 bolts and 2 compression springs.

      Torque:
      43 N*m  { 438 kgf*cm, 32 ft.*lbf }
  6. CONNECT AIR FUEL RATIO SENSOR CONNECTOR

  7. INSTALL NO. 2 ENGINE UNDER COVER


    1. A01IOL8

      Install the No. 2 engine under cover with the 4 clips.

  8. INSTALL AIR CLEANER BRACKET

    A01IR5R

    1. Install the air cleaner bracket with the 3 bolts.

      Torque:
      7.0 N*m  { 71 kgf*cm, 62 in.*lbf }
  9. INSTALL FUEL FILTER SUPPORT

    A01IQHG

    1. Install the fuel filter support with the 4 bolts.

      Torque:
      18 N*m  { 178 kgf*cm, 13 ft.*lbf }
    2. Attach the connector clamp to the fuel filter support.

    3. A01IOR8

      Connect the fuel filter assembly to the fuel filter support with the 2 nuts.

      Torque:
      18 N*m  { 178 kgf*cm, 13 ft.*lbf }
    4. Attach the 2 wire harness clamps and connector clamp, and then connect the connector to connect the engine wire to the fuel filter support.

  10. INSTALL AIR CLEANER CASE SUB-ASSEMBLY


    1. Install the air cleaner case with the 3 bolts.

      Torque:
      7.0 N*m  { 71 kgf*cm, 62 in.*lbf }
  11. INSTALL AIR CLEANER CAP AND HOSE


    1. A01INV0E02
      Text in Illustration
      *a Upper

      Connect the air cleaner hose.

      Tech Tips

      The direction of the hose clamp is indicated in the illustration.

    2. Attach the 4 clamps to install the air cleaner cap.

    3. Connect the PCV hose.

    4. Attach the clamp and connect the mass air flow meter connector.

  12. INSTALL NO. 1 ENGINE COVER


    1. A01INMI

      Attach the 4 clips to install the No. 1 engine cover.

  13. INSPECT SHIFT LEVER POSITION


    1. When moving the shift lever from P to R with the ignition switch ON and the brake pedal depressed, make sure that the shift lever moves smoothly and correctly into position.

    2. Start the engine and make sure that the vehicle moves forward after moving the shift lever from N to D and moves in reverse after moving the shift lever to R. If the operation cannot be performed as specified, inspect the park/neutral position switch assembly and check the shift lever assembly installation condition.

  14. ADJUST SHIFT LEVER POSITION


    1. Remove the lower No. 1 instrument panel finish panel Click here.

    2. Apply the parking brake and move the shift lever to N.

    3. A01IPDG

      Disconnect the end of the transmission control cable assembly from the shift lever assembly.

    4. A01ITR7E01
      Text in Illustration
      *1 Stopper
      *2 Nut

      Pull out the stopper of the transmission control cable.

      Note

      Do not remove the stopper. If the stopper is removed, reinstall it to its original position.

    5. Rotate the nut counterclockwise approximately 180° and, while holding the nut in that position, disconnect the transmission control cable from the shift lever retainer.

      Note

      Do not over-rotate the nut as it will come off the internal spring and the transmission control cable will not be reusable.

    6. A01IT4JE01

      Push the 2 claws together at the top of the transmission control cable lock piece. While holding the 2 claws together, push the 2 lugs on the bottom of the lock piece toward each other and upward to pull out the lock piece.

    7. Turn the nut of the transmission control cable 180° counterclockwise. While holding the nut in place, push in the stopper until the stopper clicks twice.

      A01ITS8E01
      Text in Illustration
      *1 Stopper *2 Nut
    8. Install the outer part of the transmission control cable to the shift lever retainer. Check that the spring is positioned at "A" and push in the stopper.

      A01IQUME01
      Text in Illustration
      *1 Stopper *2 Nut
      *3 Shift Lever Retainer *4 Spring

      Tech Tips

      If the stopper cannot be pushed in, slightly turn the nut clockwise and then push in the stopper again.

    9. A01IQXAE01

      Coat the end of the cable with MP grease.

    10. Connect the end of the cable to the shift lever.

      Text in Illustration
      *1 Lock Piece

      Note


      • Make sure that the lock piece is pulled up.

      • Push on the end of the cable all the way to the base of the pin.

    11. A01ISRAE01
      Text in Illustration
      *1 Lock Piece
      *2 Adjuster Case

      Push the lock piece into the adjuster case.

      Note

      Securely push in the lock piece until it locks.