INTEGRATION RELAY INSTALLATION


  1. INSTALL NO. 2 INTEGRATION RELAY


    1. Connect the 3 connectors.

    2. Attach the 2 claws to install the No. 2 integration relay.

  2. INSTALL NO. 1 RELAY BLOCK COVER


    1. Attach the 3 claws.

    2. Attach the 2 clamps and install the No. 1 relay block cover.

  3. INSTALL COOL AIR INTAKE DUCT SEAL


    1. Install the cool air intake duct seal with the 7 clips.

  4. INSTALL ENGINE ROOM SIDE COVER


    1. Install the engine room side cover with the 4 clips.

  5. CONNECT CABLE TO AUXILIARY BATTERY NEGATIVE TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected Click here.

  6. INSTALL LUGGAGE COMPARTMENT TRIM COVER LH


    1. Install the luggage compartment trim cover LH.

  7. INSTALL LUGGAGE COMPARTMENT FLOOR MAT


    1. Install the luggage compartment floor mat.