TRANSMISSION CONTROL CABLE INSTALLATION

PROCEDURE


  1. INSTALL TRANSMISSION CONTROL CABLE ASSEMBLY


    1. Install the transmission control cable assembly with the 3 nuts.

      Torque:
      5.0 N*m  { 51 kgf*cm, 44 in.*lbf }
    2. A005IBUE01

      Install the 2 transmission control cables with 2 new clips*1.

    3. Install the 2 clips.

  2. CONNECT TRANSMISSION CONTROL CABLE ASSEMBLY

    Click here

  3. ADJUST TRANSMISSION CONTROL CABLE ASSEMBLY

    Click here

  4. INSTALL BATTERY CARRIER

    Click here

  5. INSTALL BATTERY TRAY

    Click here

  6. INSTALL BATTERY

    Click here

  7. INSTALL LOWER INSTRUMENT PANEL CENTER FINISH PANEL

    Click here

  8. INSTALL CENTER INSTRUMENT CLUSTER FINISH PANEL ASSEMBLY

    Click here

  9. INSTALL NO. 1 METER HOOD CLUSTER

    Click here

  10. INSTALL NO. 2 METER HOOD CLUSTER

    Click here

  11. INSTALL REAR CONSOLE BOX ASSEMBLY

    Click here

  12. INSTALL FRONT NO. 2 FLOOR HEAT INSULATOR


    1. A005JU2E01
      Text in Illustration
      *a Front mark

      Install the No. 2 floor heat insulator with the nut and 2 bolts.

      Torque:
      5.5 N*m  { 56 kgf*cm, 49 in.*lbf }
  13. INSTALL FRONT EXHAUST PIPE ASSEMBLY

    Click here