PROCEDURE
INSPECT PURGE VSV
Inspect the purge VSV.
Measure the resistance according to the value(s) in the table below.
| Standard Resistance | |||||||||
|---|---|---|---|---|---|---|---|---|---|
|
If the result is not as specified, replace the purge VSV.
When measuring the coil resistance make sure that the surface temperature of the purge VSV is 20°C.
Check the operation of the purge VSV.
| *1 | Port E |
| *2 | Port F |
| *a | Does not flow |
|
Air pressure |
Check that air does not flow from port E to port F.
| *1 | Port E |
| *2 | Port F |
|
Air pressure |
Apply battery voltage to the connector and check the VSV operation.
| OK | ||||
|---|---|---|---|---|
|
If the result is not as specified, replace the purge VSV.