BATTERY BLOWER INSTALLATION


  1. INSTALL BATTERY COOLING BLOWER ASSEMBLY

    Note


    • Be sure not to touch the fan part of the battery cooling blower assembly.

    • Do not lift the battery cooling blower assembly using the wire harness.


    1. Install the battery cooling blower assembly with the 2 bolts and nut.

      Torque:
      7.5 N*m  { 76 kgf*cm, 66 in.*lbf }
    2. Connect the battery cooling blower assembly connector and clamp.

    3. Connect the 2 wire harness clamps.

  2. INSTALL NO. 1 HYBRID BATTERY INTAKE DUCT

    Note

    Ensure that the duct is installed securely.


    1. Install the No. 1 hybrid battery intake duct with the 2 clips.

  3. INSTALL REAR FLOOR BOARD SPACER


    1. Install the rear floor board spacer with the 2 clips.

  4. INSTALL REAR SEAT SIDE GARNISH RH

    Tech Tips

    Use the same procedure as for the LH side Click here.

  5. INSTALL REAR DOOR SCUFF PLATE RH

    Tech Tips

    Use the same procedure as for the LH side Click here.

  6. INSTALL REAR SEATBACK ASSEMBLY RH

    Click here

  7. INSTALL REAR NO. 1 FLOOR BOARD


    1. Engage the 2 claws and 2 clips.

    2. Install the rear No. 1 floor board with the bolt.

  8. INSTALL REAR NO. 2 FLOOR BOARD SUB-ASSEMBLY


    1. Engage the claw and 2 clips to install the rear No. 2 floor board sub-assembly.

  9. INSTALL REAR NO. 1 FLOOR BOARD SUB-ASSEMBLY


    1. Engage the 2 claws and 2 clips to install the rear No. 1 floor board sub-assembly.

  10. INSTALL TONNEAU COVER ASSEMBLY (w/ Tonneau Cover)


    1. Install the tonneau cover assembly.

  11. INSTALL DECK FLOOR BOX LH (w/o Woofer)


    1. Engage the 6 guides.

    2. Install the deck floor box LH with the clip.

  12. INSTALL REAR NO. 4 FLOOR BOARD (w/ Woofer)


    1. Engage the 2 clips and 3 guides to install the rear No. 4 floor board.

  13. INSTALL REAR NO. 4 FLOOR BOARD (w/o Woofer)


    1. Install the rear No. 4 floor board.

  14. INSTALL DECK FLOOR BOX RH


    1. Engage the 6 guides.

    2. Install the deck floor box RH with the clip.

  15. INSTALL REAR NO. 3 FLOOR BOARD


    1. Install the rear No. 3 floor board.

  16. INSTALL REAR DECK FLOOR BOX


    1. Install the rear deck floor box.

  17. INSTALL REAR NO. 2 FLOOR BOARD


    1. Install the rear No. 2 floor board.