SKID CONTROL BUZZER (for RHD) INSTALLATION


  1. INSTALL SKID CONTROL BUZZER ASSEMBLY


    1. A01JC1G

      Connect the skid control buzzer connector.

    2. Install the skid control buzzer assembly.

  2. INSTALL ECU INTEGRATION BOX RH


    1. A01JCW5

      Install the ECU integration box RH with the nut and bolt.

      Torque:
      14 N*m  { 138 kgf*cm, 10 ft.*lbf }
    2. Connect the connectors.

  3. INSTALL LOWER INSTRUMENT PANEL FINISH PANEL

    Tech Tips

    Perform the same procedure as for the LHD Click here.

  4. INSTALL COWL SIDE TRIM SUB-ASSEMBLY RH

    Tech Tips

    Perform the same procedure as for the LHD Click here.

  5. INSTALL FRONT DOOR SCUFF PLATE RH

    Tech Tips

    Perform the same procedure as for the LHD Click here.

  6. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected Click here.

  7. INSTALL REAR NO. 3 FLOOR BOARD


    1. A01JC33

      Engage the 2 guides to install the rear No. 3 floor board.

  8. INSTALL REAR DECK FLOOR BOX


    1. Install the rear deck floor box.

  9. INSTALL REAR NO. 2 FLOOR BOARD


    1. A01JCWRE01

      Engage the 3 guides <A>.

    2. Engage the 2 guides <B> and install the rear No. 2 floor board as shown in the illustration.