PURGE VALVE INSTALLATION


  1. INSTALL NO. 1 VACUUM SWITCHING VALVE


    1. A01NGJZ

      Install the No. 1 vacuum switching valve with the bolt.

      Torque:
      10 N*m  { 102 kgf*cm, 7 ft.*lbf }
    2. A01NE9XE01

      Connect the 2 fuel vapor feed hoses to the No. 1 vacuum switching valve.

    3. Connect the wire harness clamp.

    4. Connect the No. 1 vacuum switching valve connector.

  2. INSTALL V-BANK COVER SUB-ASSEMBLY


    1. A01NEB5

      Fit the 4 retainers and install the V-bank cover sub-assembly.

  3. INSTALL COOL AIR INTAKE DUCT SEAL


    1. A01NDNO

      Install the cool air intake duct seal with the 6 clips.

  4. INSTALL ENGINE ROOM SIDE COVER


    1. A01NHKG

      Install the engine room side cover with the 4 clips.

  5. INSTALL ENGINE ROOM SIDE COVER LH


    1. A01NH7B

      Engage the guide.

    2. Install the engine room side cover LH with the 4 clips.