GENERATOR INSTALLATION

PROCEDURE


  1. INSTALL GENERATOR ASSEMBLY


    1. Install the 2 wire harness clamp brackets to the generator assembly with the 3 bolts.

      Torque:
      10 N*m  { 102 kgf*cm, 7 ft.*lbf }
    2. Install the generator assembly with the 2 bolts.

      Torque:
      43 N*m  { 438 kgf*cm, 32 ft.*lbf }
    3. Engage the 4 wire harness clamps.

    4. Connect the generator assembly connector.

    5. Connect the wire harness to terminal B with the nut.

      Torque:
      12 N*m  { 122 kgf*cm, 9 ft.*lbf }
    6. Install the terminal cap.

    7. Engage the 2 wire harness clamps.

  2. INSTALL V-RIBBED BELT

    Click here

  3. INSTALL AIR CLEANER ASSEMBLY WITH NO. 2 AIR CLEANER HOSE

    Click here

  4. INSTALL INLET NO. 1 AIR CLEANER

    Click here

  5. INSTALL COOL AIR INTAKE DUCT SEAL

    Click here

  6. INSTALL ENGINE ROOM SIDE COVER

    Click here

  7. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected.

    Click here