COOLING FAN MOTOR INSTALLATION

PROCEDURE


  1. INSTALL NO. 2 COOLING FAN MOTOR


    1. Install the No. 2 cooling fan motor with the 3 screws.

      Torque:
      for 100 W Type
      2.6 N*m  { 27 kgf*cm, 23 in.*lbf }
      for 200 W Type
      3.9 N*m  { 40 kgf*cm, 35 in.*lbf }
  2. INSTALL COOLING FAN MOTOR


    1. Install the cooling fan motor with the 3 screws.

      Torque:
      3.9 N*m  { 40 kgf*cm, 35 in.*lbf }
  3. INSTALL FAN

    Note

    Do not reverse the position of the fan and No. 2 fan when installing them. Doing so may damage the parts.


    1. Install the fan with the nut.

      Torque:
      6.3 N*m  { 64 kgf*cm, 56 in.*lbf }
  4. INSTALL NO. 2 FAN

    Note

    Do not reverse the position of the fan and No. 2 fan when installing them. Doing so may damage the parts.


    1. Install the No. 2 fan with the nut.

      Torque:
      6.3 N*m  { 64 kgf*cm, 56 in.*lbf }
  5. INSTALL COOLING FAN ECU


    1. Install the cooling fan ECU with the 2 screws.

      Torque:
      2.6 N*m  { 27 kgf*cm, 23 in.*lbf }
    2. Engage the 4 clamps.

    3. Connect the cooling fan motor connector and No. 2 cooling fan motor connector.

  6. INSTALL FAN SHROUD ASSEMBLY


    1. Engage the 3 guides.

    2. Engage the 3 claws and install the fan shroud assembly to the radiator assembly.

      Note

      Do not damage the radiator assembly when installing the fan shroud assembly.

  7. INSTALL ENGINE ROOM ECU OUTLET DUCT

    Click here

  8. CONNECT ENGINE ROOM MAIN WIRE

    Click here

  9. INSTALL RADIATOR RESERVE TANK ASSEMBLY

    Click here

  10. INSTALL NO. 1 RADIATOR HOSE

    Click here

  11. INSTALL INLET NO. 1 AIR CLEANER

    Click here

  12. ADD ENGINE COOLANT

    Click here

  13. INSPECT FOR COOLANT LEAK

    Click here

  14. INSTALL NO. 1 ENGINE UNDER COVER ASSEMBLY

    Click here

  15. INSTALL V-BANK COVER SUB-ASSEMBLY

    Click here

  16. INSTALL COOL AIR INTAKE DUCT SEAL

    Click here

  17. INSTALL ENGINE ROOM SIDE COVER

    Click here