DESCRIPTION
Power is supplied to the fold seat control ECU through the ECU-B, FOLD SEAT LH*1, FOLD SEAT RH*2 and ECU-IG NO. 2 fuses.
*1: for LH Side
*2: for RH Side
WIRING DIAGRAM
INSPECTION PROCEDURE
Tech Tips
Inspect the fuses for circuits related to this system before performing the following inspection procedure.
PROCEDURE
CHECK HARNESS AND CONNECTOR (FOLD SEAT CONTROL ECU - BATTERY AND BODY GROUND)
| *A | for LHD |
| *B | for RHD |
| *a | Front view of wire harness connector (to Fold Seat Control ECU) |
for LH Side:
Disconnect the d1 and d2 ECU connectors.
for RH Side:
Disconnect the c1 and c2 ECU connectors.
Measure the voltage according to the value(s) in the table below.
| Standard Voltage | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
||||||||||||||
|
Measure the resistance according to the value(s) in the table below.
| Standard Resistance | |||||||||
|---|---|---|---|---|---|---|---|---|---|
|
|||||||||
|
| NG |
|
REPAIR OR REPLACE HARNESS OR CONNECTOR |
| OK |
|
PROCEED TO NEXT SUSPECTED AREA SHOWN IN PROBLEM SYMPTOMS TABLE Click here