Click here

STEERING LINKAGE INSPECTION

Click here
Click here Click here
  1. Click here

    INSPECT TIE ROD END SUB-ASSEMBLY LH


    1. Install the nut.

    2. Flip the ball joint stud back and forth 5 times as shown in the illustration.

    3. Using a torque wrench, turn the nut continuously at a rate of 3 to 5 seconds per turn and check the torque reading on the 5th turn.

      Torque
      0.98 to 3.92 N*m (10.0 to 35.0 kgf*cm, 8.67 to 30.36 in.*lbf)
  2. Click here

    INSPECT TOTAL PRELOAD


    1. A015DEWE01

      Put matchmarks on the dust cover and steering link.

    2. Remove the dust cover.

    3. Temporarily install the 2 steering rack ends to the power steering rack.

      Note:

      Do not fully turn the power steering rack without the steering rack ends as it may damage the oil seal in the rack housing.

    4. A0159KRE01

      Using SST, fully turn the power steering rack right and left 10 times to settle it.

      09616-00011
    5. A0158YSE01

      Using SST, turn the control valve and measure the preload.

      09616-00011
      Standard preload (turning)
      2.4 N*m (24 kgf*cm, 21 in.*lbf)

      If the turning torque is not as specified, replace the power steering link.

      Note:

      After setting the steering rack to the neutral point, align the dust cover rib with the power steering protrusion.

      Tip:
      • Measure the standard preload at the steering rack neutral point.

      • The steering control valve is fully turned when turned 3.14 times. Half of the distance from the fully turned position is the neutral point.

    6. A015DEWE01

      After inspecting the preload, align the matchmarks and install the dust cover.