REVOLUTION SENSOR INSTALLATION

PROCEDURE


  1. INSTALL TRANSMISSION REVOLUTION SENSOR (NT)


    1. Apply Toyota Genuine CVT fluid FE to a new O-ring.

    2. Install the O-ring to the transmission revolution sensor (NT).

    3. Install the transmission revolution sensor (NT) to the continuously variable transaxle assembly with the bolt.

      Torque:
      5.4 N*m  { 55 kgf*cm, 48 in.*lbf }
    4. Connect the connector.

  2. INSTALL TRANSMISSION REVOLUTION SENSOR (NOUT)


    1. Apply Toyota Genuine CVT fluid FE to a new O-ring.

    2. Install the O-ring to the transmission revolution sensor (NOUT).

    3. Install the transmission revolution sensor (NOUT) to the continuously variable transaxle assembly with the bolt.

      Torque:
      5.4 N*m  { 55 kgf*cm, 48 in.*lbf }
    4. Connect the connector.

  3. INSTALL TRANSMISSION REVOLUTION SENSOR (NIN)


    1. Apply Toyota Genuine CVT fluid FE to a new O-ring.

    2. Install the O-ring to the transmission revolution sensor (NIN).

    3. Install the transmission revolution sensor (NIN) to the continuously variable transaxle assembly with the bolt.

      Torque:
      5.4 N*m  { 55 kgf*cm, 48 in.*lbf }
    4. Connect the connector.

  4. INSTALL BATTERY CLAMP SUB-ASSEMBLY

    Click here

  5. INSTALL ECM

    Click here

  6. INSTALL AIR CLEANER CASE SUB-ASSEMBLY

    Click here

  7. INSTALL AIR CLEANER CAP WITH AIR CLEANER HOSE

    Click here

  8. INSTALL NO. 1 AIR CLEANER INLET

    Click here

  9. INSTALL RADIATOR COVER

    Click here

  10. INSTALL BATTERY

    Click here

  11. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

    Click here

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected.

    Click here

  12. INSTALL NO. 2 CYLINDER HEAD COVER

    Click here

  13. CHECK DATA LIST

    Click here