CAUTION / NOTICE / HINT
Tech Tips
Use the same procedure for the RH side and LH side.
The following procedure is for the LH side.
PROCEDURE
INSTALL ROOF DRIP SIDE FINISH MOULDING CLIP
Note
When installing new roof drip side finish moulding clips, remove the double-sided tape remaining where the roof drip side finish moulding clips will be installed on the vehicle body and clean the vehicle body with non-residue solvent.
Apply a 2 to 3 mm (0.0787 to 0.118 in.) bead of adhesive (3M DP-105 or equivalent) to 2 new roof drip side finish moulding clips.
Tech Tips
Adhesive strength (tensile strength): 13.7 MPa (140.0 kgf/cm2, 1987 psi) or more (when the temperature is 23°C (73°F).)
Install the roof drip side finish moulding clips to the positions on the roof panel shown in the illustration. Determine the locations and firmly press and install the 2 roof drip side finish moulding clips after lightly applying adhesive (3M DP-105 or equivalent).
| Standard Dimension | ||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Install the center roof drip side finish moulding when 20 minutes or more have elapsed after pressing and installing the 2 roof drip side finish moulding clips.
Tech Tips
Initial hardening time: 20 minutes
Complete hardening time: 48 hours
INSTALL CENTER ROOF DRIP SIDE FINISH MOULDING
Engage the roof drip side moulding clips to install the center roof drip side finish moulding.
Remove the protective tape.