ANTENNA CORD INSTALLATION

PROCEDURE


  1. INSTALL ANTENNA CORD SUB-ASSEMBLY


    1. Engage the guides and clamps to install the antenna cord sub-assembly.

      A01MIMTC01
      *a Guide *b Clamp
    2. A01MJZ4

      Connect the connector.

    3. Engage the claws.

  2. INSTALL NO. 4 INSTRUMENT PANEL CUSHION

    Click here

  3. INSTALL NO. 1 SIDE DEFROSTER NOZZLE DUCT

    Click here

  4. INSTALL NO. 3 HEATER TO REGISTER DUCT

    Click here

  5. INSTALL UPPER INSTRUMENT PANEL SUB-ASSEMBLY

    Click here