GENERATOR(for 90A Type) INSTALLATION

PROCEDURE


  1. INSTALL GENERATOR ASSEMBLY


    1. Install the generator assembly with the 3 bolts.

      Torque:
      43 N*m  { 438 kgf*cm, 32 ft.*lbf }
    2. Connect the wire harness to terminal B with the nut.

      Torque:
      9.8 N*m  { 100 kgf*cm, 87 in.*lbf }
    3. Install the generator bracket with the bolt.

      Torque:
      13 N*m  { 133 kgf*cm, 10 ft.*lbf }
    4. Install the terminal cap.

    5. Connect the generator connector.

  2. INSTALL FAN AND GENERATOR V BELT

    Click here

  3. INSTALL AIR CLEANER CASE SUB-ASSEMBLY

    Click here

  4. INSTALL AIR CLEANER FILTER ELEMENT SUB-ASSEMBLY

    Click here

  5. INSTALL AIR CLEANER CAP SUB-ASSEMBLY WITH NO. 1 AIR CLEANER HOSE

    Click here

  6. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected.