GENERATOR(for 90A Type) INSTALLATION

PROCEDURE


  1. INSTALL GENERATOR ASSEMBLY


    1. Install the 2 generator brackets with the 2 bolts.

      Torque:
      8.4 N*m  { 86 kgf*cm, 74 in.*lbf }
    2. Install the generator assembly with the 2 bolts.

      Torque:
      43 N*m  { 438 kgf*cm, 32 ft.*lbf }
    3. Attach the 3 clamps and connect the wire harness.

    4. Connect the wire harness to terminal B with the nut.

      Torque:
      9.8 N*m  { 100 kgf*cm, 87 in.*lbf }
    5. Install the terminal cap.

    6. Connect the generator connector and attach the clamp.

    7. Connect the intake air temperature sensor connector.

  2. INSTALL FAN AND GENERATOR V BELT

    Click here

  3. INSTALL NO. 4 AIR HOSE

    Click here

  4. INSTALL BATTERY TRAY

  5. INSTALL BATTERY

  6. INSTALL BATTERY CLAMP SUB-ASSEMBLY


    1. Install the battery clamp sub-assembly with the 2 nuts and 2 battery clamp bolts.

      Torque:
      5.4 N*m  { 55 kgf*cm, 48 in.*lbf }
  7. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected.

    Click here