PARK / NEUTRAL POSITION SWITCH INSTALLATION

PROCEDURE


  1. INSTALL PARK/NEUTRAL POSITION SWITCH ASSEMBLY


    1. Temporarily install the park/neutral position switch assembly to the automatic transaxle case sub-assembly with the 2 bolts.

      Note

      Before installing the park/neutral position switch assembly, remove any dirt or rust on the manual valve lever shaft sub-assembly. Be sure to install the park/neutral position switch assembly straight along the manual valve lever shaft sub-assembly while being careful not to deform the plate spring that supports the manual valve lever shaft sub-assembly. If the plate spring is deformed, the park/neutral position switch assembly cannot be installed correctly.

    2. Temporarily install the transmission control shaft lever to the park/neutral position switch assembly.

    3. B006R5BC01
      *a P
      *b N

      Turn the transmission control shaft lever clockwise until it stops, then turn it counterclockwise 2 notches.

    4. Remove the transmission control shaft lever from the park/neutral position switch assembly.

    5. B006P9JC01
      *a Neutral Basic Line
      *b Protrusion

      Align the protrusion with the neutral basic line.

    6. Hold the park/neutral position switch assembly in that position and tighten the 2 bolts.

      Torque:
      5.4 N*m  { 55 kgf*cm, 48 in.*lbf }
    7. Install the transmission control shaft lever to the manual valve lever shaft sub-assembly with the washer and nut.

      Torque:
      12.7 N*m  { 130 kgf*cm, 9 ft.*lbf }
    8. Connect the park/neutral position switch assembly connector.

  2. CONNECT TRANSMISSION CONTROL CABLE ASSEMBLY


    1. B006P0EC01
      *a Correct
      *b Incorrect

      Connect the transmission control cable assembly to the transmission control shaft lever as shown in the illustration.

      Note

      Before connecting the transmission control cable assembly, check that the park/neutral position switch assembly and shift lever are in N.

  3. INSTALL AIR CLEANER CASE SUB-ASSEMBLY

    Click here

  4. INSTALL AIR CLEANER CAP WITH AIR CLEANER HOSE

    Click here

  5. INSTALL BATTERY

    Click here

  6. INSTALL V-BANK COVER SUB-ASSEMBLY

    Click here

  7. INSTALL CENTER NO. 1 COWL TOP VENTILATOR LOUVER

    Click here

  8. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected.

    Click here

  9. INSPECT PARK/NEUTRAL POSITION SWITCH ASSEMBLY OPERATION

    Click here

  10. INSPECT SHIFT LEVER POSITION

    Click here

  11. ADJUST SHIFT LEVER POSITION

    Click here