PCV VALVE INSTALLATION

PROCEDURE


  1. INSTALL PCV VALVE SUB-ASSEMBLY


    1. Apply a light coat of engine oil to the O-ring.

    2. A01XNNYC02
      *a Torque Wrench Fulcrum Length
      *b 22 mm Ball Joint Lock Nut Wrench

      Using a 22 mm ball joint lock nut wrench, install the PCV valve sub-assembly to the cylinder head cover sub-assembly.

      Torque
      Specified tightening torque
      5.0 N*m (51 kgf*cm, 44 in.*lbf)

      Note

      When reusing the PCV valve sub-assembly, inspect the O-ring.

      Tech Tips


      • Calculate the torque wrench reading when changing the fulcrum length of the torque wrench.

        Click here

      • When using a ball joint lock nut wrench (fulcrum length of 149.75 mm (5.90 in.)) + torque wrench (fulcrum length of 185 mm (7.28 in.)): 2.8 N*m (29 kgf*cm, 25 in.*lbf)

    3. Connect the No. 2 PCV hose to the PCV valve sub-assembly, and slide the clip to secure the hose.

  2. INSTALL NO. 1 ENGINE COVER SUB-ASSEMBLY

    Click here