COMBINATION METER INSTALLATION

PROCEDURE


  1. INSTALL COMBINATION METER ASSEMBLY


    1. Connect each connector.

    2. A00YN66

      Engage the 2 clips as shown in the illustration.

    3. Install the combination meter assembly with the 2 screws.

  2. INSTALL INSTRUMENT CLUSTER FINISH PANEL ASSEMBLY

    Click here

  3. INSTALL NO. 1 METER HOOD CLUSTER

    Click here

  4. INSTALL CENTER INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY

    Click here

  5. INSTALL LOWER NO. 2 INSTRUMENT PANEL FINISH PANEL

    Click here

  6. CONNECT CABLE TO AUXILIARY BATTERY NEGATIVE TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected.

    Click here

  7. INSTALL BATTERY BOX COVER

    Click here