POWER MANAGEMENT CONTROL ECU(for RHD) INSTALLATION

PROCEDURE


  1. INSTALL POWER MANAGEMENT CONTROL ECU


    1. Install the power management control ECU with the 2 bolts.

      Torque:
      8.0 N*m  { 82 kgf*cm, 71 in.*lbf }
    2. Connect each connector.

  2. INSTALL GLOVE COMPARTMENT DOOR ASSEMBLY

    Click here

  3. INSTALL NO. 2 INSTRUMENT PANEL UNDER COVER SUB-ASSEMBLY

    Click here

  4. CONNECT CABLE TO NEGATIVE AUXILIARY BATTERY TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected.

    Click here

  5. INSTALL BATTERY BOX COVER

    for Hatchback: Click here

    for Wagon: Click here