POWER MANAGEMENT CONTROL ECU(for LHD) INSTALLATION

PROCEDURE


  1. INSTALL POWER MANAGEMENT CONTROL ECU

    A01G406

    1. Engage the 2 claws to install the power management control ECU as shown in the illustration.

  2. INSTALL ECU INTEGRATION BOX RH


    1. Engage the guide and install the ECU integration box RH with the 3 bolts.

      Torque:
      12 N*m  { 122 kgf*cm, 9 ft.*lbf }
    2. Engage the 2 clamps.

    3. Connect each connector.

    4. Engage the 2 clamps.

  3. INSTALL GLOVE COMPARTMENT DOOR ASSEMBLY

    Click here

  4. INSTALL NO. 2 INSTRUMENT PANEL UNDER COVER SUB-ASSEMBLY (w/ Instrument Panel Under Cover)

    Click here

  5. CONNECT CABLE TO NEGATIVE AUXILIARY BATTERY TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected.

    Click here

  6. INSTALL BATTERY BOX COVER

    for Hatchback: Click here

    for Wagon: Click here