CLEARANCE WARNING ECU(for LHD) INSTALLATION

PROCEDURE


  1. INSTALL CLEARANCE WARNING ECU ASSEMBLY


    1. Engage the 2 claws to install the clearance warning ECU assembly.

  2. INSTALL ECU INTEGRATION BOX RH


    1. Install the ECU integration box RH with the 3 bolts.

      Torque:
      12 N*m  { 122 kgf*cm, 9 ft.*lbf }
    2. Connect each connector.

  3. INSTALL GLOVE COMPARTMENT DOOR ASSEMBLY

    Click here

  4. INSTALL NO. 2 INSTRUMENT PANEL UNDER COVER SUB-ASSEMBLY (w/ Instrument Panel Under Cover)

    Click here

  5. CONNECT CABLE TO AUXILIARY BATTERY NEGATIVE TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected.

    Click here

  6. INSTALL BATTERY BOX COVER

    Click here