ГЕНЕРАТОР УСТАНОВКА

PROCEDURE


  1. INSTALL GENERATOR ASSEMBLY


    1. B00446AC01

      Install the generator assembly with the 2 bolts.

      Torque:
      for bolt A
      35 N*m  { 357 kgf*cm, 26 ft.*lbf }
      for bolt B
      54 N*m  { 551 kgf*cm, 40 ft.*lbf }
    2. B0041P4

      Connect the wire harness to terminal B and install the nut.

      Torque:
      9.8 N*m  { 100 kgf*cm, 87 in.*lbf }
    3. Connect the connector and 2 clamps.

    4. Install the terminal cap.

  2. INSTALL V-RIBBED BELT

    Click here

  3. INSTALL NO. 1 ENGINE COVER (w/ No. 1 Engine Cover)

    Click here

  4. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected.

    Click here