СВЕЧА НАКАЛИВАНИЯ УСТАНОВКА

PROCEDURE


  1. INSTALL GLOW PLUG ASSEMBLY


    1. Using a 12 mm deep socket wrench, install the 4 glow plugs.

      Torque:
      13 N*m  { 130 kgf*cm, 10 ft.*lbf }
  2. INSTALL NO. 1 GLOW PLUG CONNECTOR


    1. Install the No. 1 glow plug resistor insulator and No. 1 glow plug connector.

    2. B001DNUE01
      Text in Illustration
      *1 Nut
      *2 Washer
      *3 No. 2 Glow Plug Resistor Insulator
      *4 Engine Wire
      *5 No. 1 Glow Plug Connector
      *6 No. 1 Glow Plug Resistor Insulator
      *7 Bolt

      Install the glow plug connector with the 4 nuts. Uniformly tighten the nuts.

      Torque:
      1.0 N*m  { 10 kgf*cm, 9 in.*lbf }
    3. Install the 4 screw grommets.

    4. Connect the engine wire and install the No. 2 glow plug resistor insulator and washer with the bolt.

      Torque:
      5.0 N*m  { 51 kgf*cm, 44 in.*lbf }
  3. CONNECT VENTILATION HOSE


    1. Connect the ventilation hose.

  4. INSTALL INTAKE PIPE

    Click here

  5. INSTALL RESONATOR WITH AIR CLEANER CAP SUB-ASSEMBLY

    Click here

  6. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected Click here.