ТОПЛИВНАЯ ФОРСУНКА УСТАНОВКА

PROCEDURE


  1. INSTALL NOZZLE HOLDER AND NOZZLE SET


    1. B001EBFE04

      Install 4 new injection nozzle seat gaskets and the 4 injection nozzle seats to the injection nozzle holes of the cylinder head.

    2. Using SST, install the 4 nozzle holder and nozzle sets.

      SST
      09268-64010   ( 09268-64020 )
      Torque:
      64 N*m  { 650 kgf*cm, 47 ft.*lbf }
  2. INSTALL NOZZLE LEAKAGE PIPE ASSEMBLY


    1. Install 4 new ring packing washers and the leakage pipe with the 4 nuts.

      Torque:
      30 N*m  { 301 kgf*cm, 22 ft.*lbf }
    2. Connect the fuel hose to the leakage pipe.

  3. INSTALL NO. 1 GLOW PLUG CONNECTOR

    Click here

  4. INSTALL INJECTION PIPE SET


    1. Install the 2 lower clamps to the intake manifold.

    2. B001GI1E01
      Text in Illustration
      *a for Injection Nozzle Side
      *b for Injection Pump Side

      Install the 4 injection pipes.

      Torque:
      25 N*m  { 250 kgf*cm, 18 ft.*lbf }

      Note

      Use the formula to calculate special torque values for situations where a union nut wrench is combined with a torque wrench Click here.

    3. Install the 2 upper pipe clamps with the 2 nuts.

      Torque:
      5.0 N*m  { 51 kgf*cm, 44 in.*lbf }
  5. INSTALL DIESEL THROTTLE BODY


    1. Install the diesel throttle body Click here.

  6. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected Click here.

  7. BLEED INJECTION PIPE


    1. Move the hand pump on the upper part of the fuel filter up and down and fill the injection pump and fuel system with fuel.

    2. Loosen one of the union nuts (on the nozzle side).

    3. Crank the engine until fuel comes out from the union nut connection (on the nozzle side).

    4. Tighten the union nut.

      Torque:
      25 N*m  { 250 kgf*cm, 18 ft.*lbf }

      Note

      Use the formula to calculate special torque values for situations where a union nut wrench is combined with a torque wrench Click here.

    5. Perform the procedures above for each injection pipe.

  8. INSPECT FOR FUEL LEAK

    Click here