CONTINUOUSLY VARIABLE TRANSAXLE FLUID REPLACEMENT

PROCEDURE


  1. REMOVE REAR ENGINE UNDER COVER LH (for 1ZR-FAE)

    Click here

  2. REMOVE REAR ENGINE UNDER COVER LH (for 8NR-FTS)

    Click here

  3. REPLACE CONTINUOUSLY VARIABLE TRANSAXLE FLUID


    1. Lift the vehicle. [*1]

      Note

      Set the vehicle on a lift so that the vehicle is kept level when it is lifted up (make sure that the tilt angle from the front to rear of the vehicle is within +/- 1°).

    2. A00311I

      Remove the refill plug and gasket from the rear transaxle case. [*2]

    3. A0030IM

      Using a 6 mm hexagon socket wrench, remove the overflow plug and gasket from the transaxle oil (CVT) pan sub-assembly. [*3]

    4. A0030DMC01
      *1 No. 1 Transmission Oil Filler Tube

      Using a 6 mm hexagon socket wrench, remove the No. 1 transmission oil filler tube from the transaxle oil (CVT) pan sub-assembly and drain the fluid. [*4]

    5. A00312K

      Measure the amount of fluid drained. [*5]

      Tech Tips

      Add the same amount of fluid in step [*8].

    6. A0030DMC01
      *1 No. 1 Transmission Oil Filler Tube

      Using a 6 mm hexagon socket wrench, install the No. 1 transmission oil filler tube to the transaxle oil (CVT) pan sub-assembly. [*6]

      Torque:
      1.7 N*m  { 17 kgf*cm, 15 in.*lbf }
    7. A0030IM

      Using a 6 mm hexagon socket wrench, temporarily install the gasket and overflow plug to the transaxle oil (CVT) pan sub-assembly. [*7]

      Tech Tips

      Reuse the old gasket as the overflow plug will be removed again when flushing the fluid.

    8. A00316I

      Add fluid to the refill hole using the same amount of fluid drained in step [*5]. [*8]

      Note

      Use Toyota Genuine CVT Fluid FE.

    9. A00311I

      Temporarily install the gasket and refill plug to the rear transaxle case. [*9]

      Tech Tips

      Reuse the old gasket as the refill plug will be removed again when flushing the fluid.

    10. Lower the vehicle. [*10]

    11. Start the engine. [*11]

    12. Slowly move the shift lever from P to D, and then back to P (keep the shift lever in each position for approximately 3 seconds). [*12]

      Tech Tips

      Slowly move the shift lever to circulate the fluid through each part of the continuously variable transaxle assembly.

    13. Allow the engine assembly to idle for 30 seconds to warm it up. [*13]

    14. Turn the ignition switch off. [*14]

    15. Repeat steps [*1] to [*14].

    16. Repeat steps [*1] to [*10].

  4. ADD SPECIFIED AMOUNT OF FLUID

    Click here

  5. AIR BLEED OIL PUMP WITH MOTOR ASSEMBLY (for 8NR-FTS)

    Click here

  6. ADJUST FLUID TEMPERATURE (when Using the GTS)

    Click here

  7. ADJUST FLUID TEMPERATURE (when Not Using the GTS)

    Click here

  8. ADJUST FLUID LEVEL

    Click here

  9. REBUILD WORK

    Click here

  10. INSTALL REAR ENGINE UNDER COVER LH (for 1ZR-FAE)

    Click here

  11. INSTALL REAR ENGINE UNDER COVER LH (for 8NR-FTS)

    Click here