VACUUM REGULATING VALVE INSTALLATION

PROCEDURE


  1. INSTALL VACUUM REGULATING VALVE ASSEMBLY


    1. Install the vacuum regulating valve assembly to the No. 2 vacuum switching valve bracket with the 2 bolts.

      Torque:
      10 N*m  { 102 kgf*cm, 7 ft.*lbf }
    2. Connect the No. 2 vacuum transmitting hose assembly and No. 3 vacuum transmitting hose assembly to the vacuum regulating valve assembly.

    3. Connect the vacuum regulating valve assembly connector.

  2. INSTALL OUTER COWL TOP PANEL (for LHD)

    Click here

  3. INSTALL OUTER COWL TOP PANEL (for RHD)

    Click here

  4. INSTALL NO. 2 HEATER AIR DUCT SPLASH SHIELD SEAL (for LHD)

    Click here

  5. INSTALL NO. 2 HEATER AIR DUCT SPLASH SHIELD SEAL (for RHD)

    Click here

  6. INSTALL WATER GUARD PLATE LH (for LHD)

    Click here

  7. INSTALL WATER GUARD PLATE LH (for RHD)

    Click here

  8. INSTALL WINDSHIELD WIPER MOTOR AND LINK ASSEMBLY

    Click here