THERMOSTAT INSTALLATION

PROCEDURE


  1. INSTALL THERMOSTAT


    1. Install a new gasket to the thermostat.

    2. A00Y7DMC02
      *a Jiggle Valve

      Install the thermostat with the jiggle valve facing upward.

      Tech Tips

      The jiggle valve may be set within 10° on either side of the prescribed position.

  2. INSTALL WATER INLET


    1. Install the water inlet with the 3 bolts.

      Torque:
      11 N*m  { 112 kgf*cm, 8 ft.*lbf }
  3. INSTALL NO. 4 WATER BY-PASS PIPE


    1. Apply soapy water to a new O-ring and install it to the No. 4 water by-pass pipe.

    2. Install the No. 4 water by-pass pipe with the bolt.

      Torque:
      11 N*m  { 112 kgf*cm, 8 ft.*lbf }
    3. Connect the water by-pass hose and slide the clip to secure it.

  4. CONNECT NO. 2 RADIATOR HOSE


    1. Connect the No. 2 radiator hose and slide the clip to secure it.

  5. ADD ENGINE COOLANT

    Click here

  6. INSPECT FOR COOLANT LEAK

    Click here