PARK / NEUTRAL POSITION SWITCH INSTALLATION

PROCEDURE


  1. INSTALL PARK/NEUTRAL POSITION SWITCH ASSEMBLY


    1. Temporarily install the park/neutral position switch assembly to the continuously variable transaxle assembly with the 2 bolts.

    2. A002LR2

      Install the lock plate and lock nut to the park/neutral position switch assembly.

      Torque:
      6.9 N*m  { 70 kgf*cm, 61 in.*lbf }
    3. Temporarily install the control shaft lever.

    4. A002QCBE01
      Text in Illustration
      *a P Position
      *b N Position

      Turn the control shaft lever clockwise until it stops, then turn it counterclockwise 2 notches.

    5. Remove the control shaft lever from the park/ neutral position switch assembly.

    6. A002QEVE06
      Text in Illustration
      *a Neutral Basic Line
      *b Protrusion

      Align the protrusion with the neutral basic line.

    7. Hold the park/neutral position switch assembly in that position and tighten the 2 bolts.

      Torque:
      5.4 N*m  { 55 kgf*cm, 48 in.*lbf }
    8. A002OMU

      Using a screwdriver, stake the lock nut with the lock plate.

    9. Install the control shaft lever to the park/neutral position switch assembly with the nut and washer.

      Torque:
      13 N*m  { 130 kgf*cm, 9 ft.*lbf }
    10. Connect the park/neutral position switch assembly connector.

  2. INSTALL TRANSMISSION CONTROL CABLE ASSEMBLY


    1. Install the transmission control cable assembly to the No. 1 transmission control cable bracket with a new clip.

    2. Install the transmission control cable assembly to the control shaft lever with the nut.

      Torque:
      12 N*m  { 122 kgf*cm, 9 ft.*lbf }
  3. INSTALL BATTERY CARRIER

    Click here

  4. INSTALL RADIATOR PIPE

    Click here

  5. INSTALL BATTERY TRAY

  6. INSTALL BATTERY

  7. INSTALL BATTERY CLAMP SUB-ASSEMBLY

    Click here

  8. INSTALL AIR CLEANER CASE SUB-ASSEMBLY

    Click here

  9. INSTALL AIR CLEANER FILTER ELEMENT SUB-ASSEMBLY

  10. INSTALL AIR CLEANER CAP SUB-ASSEMBLY

    Click here

  11. INSTALL NO. 2 CYLINDER HEAD COVER

    Click here

  12. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL


    1. Connect the cable to the negative (-) battery terminal.

      Torque:
      5.4 N*m  { 55 kgf*cm, 48 in.*lbf }

      Note

      When disconnecting the cable, some systems need to be initialized after the cable is reconnected Click here.

  13. INSPECT PARK/NEUTRAL POSITION SWITCH ASSEMBLY OPERATION

    Click here

  14. ADJUST PARK/NEUTRAL POSITION SWITCH ASSEMBLY

    Click here

  15. INSPECT SHIFT LEVER POSITION

    Click here

  16. ADJUST SHIFT LEVER POSITION

    Click here