PCV VALVE INSTALLATION

PROCEDURE


  1. INSTALL PCV VALVE SUB-ASSEMBLY


    1. Apply adhesive to 2 or 3 threads of the PCV valve sub-assembly.

      Adhesive
      Toyota Genuine Adhesive 1324, Three Bond 1324 or equivalent
    2. Using a 19 mm deep socket wrench, install the PCV valve sub-assembly to the cylinder head cover sub-assembly.

      Torque:
      27 N*m  { 275 kgf*cm, 20 ft.*lbf }

      Note

      Do not start the engine for at least 1 hour after installation.

    3. Connect the PCV hose to the PCV valve sub-assembly and slide the clamp to secure the hose.

  2. INSTALL NO. 1 ENGINE COVER SUB-ASSEMBLY

    Click here