HORN INSPECTION

PROCEDURE


  1. INSPECT LOW PITCHED HORN ASSEMBLY

    A01XJBME02
    Text in Illustration
    *1 Terminal 1

    1. Apply battery voltage and check the operation of the horn according to the table below.

      OK
      Measurement Condition Specified Condition
      Battery positive (+) → Terminal 1 Battery negative (-) → Body ground Low pitched horn sounds

      If the result is not as specified, replace the low pitched horn assembly.

  2. INSPECT HIGH PITCHED HORN ASSEMBLY

    A01XJBME02
    Text in Illustration
    *1 Terminal 1

    1. Apply battery voltage and check the operation of the horn according to the table below.

      OK
      Measurement Condition Specified Condition
      Battery positive (+) → Terminal 1 Battery negative (-) → Body ground High pitched horn sounds