GENERATOR INSTALLATION

PROCEDURE


  1. INSTALL GENERATOR ASSEMBLY


    1. Install the generator assembly with the 3 bolts.

      Torque:
      43 N*m  { 438 kgf*cm, 32 ft.*lbf }
    2. Connect the wire harness to terminal B with the nut.

      Torque:
      9.8 N*m  { 100 kgf*cm, 87 in.*lbf }
    3. Install the terminal cap.

    4. Connect the connector to the generator assembly.

  2. INSTALL FAN AND GENERATOR V BELT

    Click here

  3. INSTALL AIR CLEANER CAP SUB-ASSEMBLY WITH AIR CLEANER HOSE

    Click here

  4. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

    Note

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected Click here.