COMBINATION SWITCH INSTALLATION

PROCEDURE


  1. INSTALL NO. 2 COMBINATION SWITCH ASSEMBLY (w/o Module Switch (2nd Start))


    1. B001GTG

      Attach the 4 claws and install the No. 2 combination switch assembly (w/o Module Switch (2nd Start)) to the lower console panel sub-assembly.

    2. Install the lower console panel sub-assembly.

      Click here

  2. INSTALL COMBINATION SWITCH ASSEMBLY (w/ Module Switch (2nd Start))


    1. B001DAF

      Connect the clamp and 4 connectors to install the combination switch assembly (w/ Module Switch (2nd Start)).

    2. B001F19

      Attach the 3 claws and install the 2 bolts to the instrument panel.

    3. Install the integration control and panel assembly.

      Click here

    4. Install the center instrument cluster finish panel sub-assembly.

      Click here