Tech Tips
Use the same procedure for the RH side and LH side.
The following procedure is for the LH side.
INSTALL NO. 1 ROOF DRIP SIDE FINISH MOULDING CLIP
Note
When installing new clips, remove the double-sided tape remaining where the clips will be installed on the body and clean the body with a non-residue solvent.
| *a | Adhesive |
| *b | 2 to 3 mm Bead of Adhesive |
Apply a 2 to 3 mm (0.0787 to 0.118 in.) bead of adhesive (3M DP-105 or equivalent) to new No. 1 roof drip side finish moulding clips.
Tech Tips
Adhesive strength (tensile strength): 13.7 MPa (140.0 kgf/cm2, 1987 psi) or more (when the temperature is 23°C (73°F))
Install the No. 1 roof drip side finish moulding clips to the positions on the roof panel shown in the illustration. Determine the locations and firmly press and install the 2 No. 1 roof drip side finish moulding clips after lightly applying adhesive.
| *A | for Front | *B | for Rear |
| *1 | Protruding Part | - | - |
| Standard Measurement | ||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Install the center roof drip side finish moulding when 20 minutes or more have elapsed after pressing and installing the 2 No. 1 roof drip side finish moulding clips.
Tech Tips
Initial hardening time: 20 minutes
Complete hardening time: 48 hours
INSTALL CENTER ROOF DRIP SIDE FINISH MOULDING
Engage the 2 No. 1 roof drip side finish moulding clips and install the center roof drip side finish moulding.